What is it for?
It tells you how much material to buy and how much it will cost to enclose a plot with a brick wall. For a 30 × 20 m plot, the total length is the perimeter: 100 m.
You can include or remove the columns with their tie beam and the strip footing, and replace each price with the one you get in your area.
How it is calculated
- Bricks: wall area, without the width of the columns, divided by the area of one brick with its joint, plus waste.
- Mortar: wall volume minus brick volume, split into cement and sand by the chosen ratio.
- Columns and tie beam: one column every 3 m and one at each end, and the beam along the top of the wall, with the sizes you choose. They use 350 kg of cement per m³ of concrete and about 3.3 kg of steel per meter. Bricks go up to the underside of the beam.
- Column and beam formwork: about 99 board feet of timber and 2.2 kg of nails per m³ of concrete, assuming the timber is reused.
- Strip footing: cyclopean concrete with 125 kg of cement per m³ and 30% stone.
- Labor: by work item, from a unit price analysis: excavation and footing per m³, bricklaying per m², columns and beam per m³ of concrete, and steel fixing per kg.
Keep in mind
- The amounts of columns, steel and footing are typical for walls up to 3 m high. A taller wall or soft soil needs an engineer's review.
- The brick and the cement bag change with the selected country. You can adjust them in the details.
- Prices vary between cities and suppliers. Always ask for a quote before buying.